Question 1 (a) Project 1 (15 marks)
You are managing a project that is scheduled to take 12 months to complete and has a budgeted actual cost (BAC) of $2,100,000.
At the Status Date, the project has the following characteristics:
Planned value (PV) $600,000 Actual cost (AC) $650,000 Percentage of work completed 26%
Calculate the following quantities:
Earned Value (EV)
Cost Variance (CV)
Schedule Variance (SV) (2 marks) Cost performance index (CPI) (2 marks) Schedule performance index (SPI) (2 marks) Using your results, apply the following three (3) formulae to the calculation of the Estimate at Completion (EAC) of the project. These formulae, and an explanation of their use, are listed in Table 7-1 on page 267 of the text:
EAC=BAC/CPI EAC=AC + (BAC EV) EAC= AC + [(BAC-EV) / (CPI x SPI)].
(4 marks)
SUB- TOTAL FOR QUESTION 1 (a)
You are managing a second project that has the same time and cost specifications as those in Question 1 (a), but which is 38% complete at the Status Date, when Actual Costs are $650,000.
Its specifications are below
Budgeted Actual Cost (BAC): $2,100,000. Schedule time to complete: 12 months
At the Status Date, the project has the following characteristics:
Planned value (PV) $600,000
4
Actual cost (AC) $650,000 Percentage of work completed 38%
Calculate the following quantities:
Earned Value (EV)
(3 marks)
Cost Variance (CV) Schedule Variance (SV) (2 marks) Cost performance index (CPI) Schedule performance index (SPI) (2 marks) Using your results, apply the following three (3) formulae to the calculation of the Estimate at Completion (EAC) of the project. These formulae, and an explanation of their use, are listed in Table 7-1 on page 267 of the text:
EAC=BAC/CPI EAC=AC + (BAC EV) EAC= AC + [(BAC-EV) / (CPI x SPI)].
SUB- TOTAL FOR Question 1 (b)
Question 1 (c) (about 500 words)
Compare the two projects from the point view of project performance, paying particular attention to the following: Cost Variance (CV) Schedule Variance (SV) (2 marks per project) Cost performance index (CPI) (2 marks per project) Schedule performance index (SPI) (2 marks per project) Estimated Actual Cost (EAC) of the project (2 marks per project) A brief assessment of the overall project performance, including any necessary measures required to successfully complete the project (5 marks per project) Total Marks per project 15 marks per project SUB- TOTAL FOR Question 1 (c)
Read less
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more