As mentioned in prior assignments, assume that you are the project manager for the Recreation and Wellness Intranet Project and that the project cost must not exceed $200,000 and must not take longer than 6 months to complete. Assume that this project cost only includes labor costs.
The following resources are available to work full time on this project. Their associated hourly labor rates is also provided below:
Project Manager: $120 per hour
Network Engineer: $95 per hour
System Design Engineer: $90 per hour
Senior Programmer/Analyst: $85 per hour
Programmer/Analyst: $75 per hour
System Test Engineer: $75 per hour
Software Test Engineer: $65 per hour
Support Team Manager: $55 per hour
Refer to Appendix A in the textbook for guidance in using Microsoft Project.
In your Microsoft Project file that you completed for last week’s assignment, enter the resources listed above into the “Resource Name” field on the Microsoft Project Resource Sheet. Be sure to enter the labor rate information into the “Std Rate” field. Do not alter any of the other fields on the Resource Sheet.
You have met with the project team and have determined which tasks each person will be assigned to. This information is located in “Recreation and Wellness Intranet Project Resource Assignments.” Based on this information, assign the resources to each task in your Microsoft Project file. Do not alter the resource hours and do not change any task durations or start/finish dates.
Read the “Resource Histograms” section in Appendix A in the textbook. Balancing resources is crucial in project planning since we want to ensure the resources are not assigned to more than number of hours in a given work week. Review the Resource Graph for your project in Microsoft Project. Resolve any resource over-allocations by manually reducing the hours for the relevant resources for relevant tasks. Make realistic adjustments to the hours (note that the work-week is 56 hours since Saturdays and Sundays are work days on this project).
Do not alter any resource task assignments.
Do not change any task durations or start/finish dates.
Do not use the Resource Leveling feature in Microsoft Project –- it may result in undesired changes to your project durations, start/finish dates, and/or resource hour allocations.
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more