McGee Carpet and Trim installs carpets in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are provided in a given table. Following are the activities that are required to install the carpets in the offices:
· Activity 1: Measure office room dimensions
· Activity 2: Estimate cost
· Activity 3: Material requisition
· Activity 4: Workforce requisition
· Activity 5: Special tool requisition
· Activity 6: Installation
· Activity 7: Inspection and customer acceptance
Activity 2 starts immediately after Activity 1. Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2. Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed. The carpet installation project is complete after Activity 7 is completed. If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:
Activities |
OT |
MT |
PT |
Activity 1 |
4 |
6 |
14 |
Activity 2 |
5 |
12 |
16 |
Activity 3 |
7 |
15 |
23 |
Activity 4 |
13 |
16 |
28 |
Activity 5 |
17 |
20 |
35 |
Activity 6 |
20 |
32 |
50 |
Activity 7 |
5 |
6 |
13 |
You must also do the following:
· Determine the expected completion time and the variance for each activity
· Determine the total project completion time and the critical path for the project
· Determine Early Start (ES), Early Finish (EF), Late Start (LS), and slack for each activity
· What is the probability that McGee Carpet and Trim will finish the project in 40 days or less?
· Define project management and the necessary requirements.
· Analyze implications of changes in project scheduling.
· Evaluate application of project management techniques in terms of the firm’s business operational goals and requirements.
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more