Problem 17-13
Here is a list of activity times for a project as well as crashing costs for its activities. Determine which activities should be crashed and the total cost of crashing if the goal is to shorten the project by three weeks as cheaply as possible. (Omit the “$” sign in your response.)
ActivityDuration (weeks)First CrashSecond Crash1-25$8 $10 2-467 9 4-7314 15 1-339 11 3-478 9 1-5510 15 5-6511 13 6-7512 14
Activity Cost First crash(Click to select)1-31-21-5
$ Second crash(Click to select) 2-4 and 3-4, 2-4 and 5-6, 3-4 and 5-6
$ Third crash(Click to select)4-7 and 6-7, 5-6 and 6-7, 4-7 and 3-4
$
Show more
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more