1) When a program deviation occurs, the Program Manager should notify the Milestone Decision Authority within 90 days of the occurrence.

1) When a program deviation occurs, the Program Manager should notify the Milestone Decision Authority within 90 days of the occurrence.

   True

   False

2) The _______ defines design requirements and is primarily documented by the Item Performance Specifications.

   Allocated Baseline

   Product Baseline

   Functional Baseline

   Maintenance Baseline

3) Who usually controls the “build to” or product baseline in an acquisition program?

   DoD Information Technology Standards Registrar

   Government

   Contractor

   Subject Matter Expert

4) The Program Manager just received approval of his proposed acquisition strategy with one exception: he has been directed to make maximum use of existing Air Force software. Which of the best software acquisition practices is most applicable to his situation?

   Inspect requirements and design

   Use system based software design

   Use metrics to manage

   Assess reuse risks and cost

5) An Early Operational Assessment is typically conducted to _____________________.

   Identify potential operational effectiveness and suitability issues during system development

   Support the decision to begin low rate initial production (LRIP)

   Meet the requirement to conduct initial operational test and evaluation (IOT&E)

   Track the evolution of critical technical parameters against the system design

6) Problem-solving models typically involve identifying all possible causes, and then narrowing down the critical causal factors to uncover the root cause.

   True

   False

7) Cost, schedule, and performance parameters are interrelated, and a change in one parameter can affect the others. Therefore it is important to involve all the key stakeholders when considering changes to the Acquisition Program Baseline (APB).

   True

   False

8) Which of the following configuration baselines is used to define the overall system level capabilities of a system?

   Functional Baseline

   Item Baseline

   Product Baseline

   Allocated Baseline

9) The primary system interoperability issue is the complete, accurate, and timely transfer of information from one system to another. In order to validate the interoperability of systems, extensive testing is required.

   True

   False

10) The management of internal interface design would usually be the responsibility of the _____________?

   Joint Interoperability Test Command

   Contractor

   Government Program Manager

   Independent Test and Evaluation Agency

11) When using the cause-and-effect (Fishbone) diagram to resolve an acquisition problem, after drawing out a blank fishbone diagram, the next step is to ____________________.

   Identify major cause categories

   Identify the root cause

   Identify possible causes and contributing factors

   Define the problem

12) What are some of the planning challenges that must be considered when taking commercial items and modifying them for military use (Select all that apply)?

   Maintain technical data

   Management of government furnished equipment

   Integration

   Long-term logistics support

   Availability of test ranges and personnel

13) Where would the initial Functional Baseline be reviewed to ensure that it covers all the Government’s capability needs?

   Critical Design Review

   Preliminary Design Review

   Systems Functional Review

   Test Readiness Review

14) Which technical review is held during the Engineering and Manufacturing Development Phase to assess the final design after the “build to” baseline has been achieved?

   Preliminary Design Review (PDR)

   Test Readiness Review (TRR)

   Critical Design Review (CDR)

   System Requirements Review (SRR)

15) Which of the following is a benefit of integrated developmental testing and operational testing?

   It minimizes the risk of compromising test objectives.

   It helps to save resources by eliminating redundant activities.

   It is required by law.

   It simplifies the test process by making tests easier to coordinate and design.

16) Program cost increases and schedules slips are most likely caused by __________________, changes to the design, and changes to the production processes.

   Changes to the number of systems ordered

   Robust and accurate configuration management

   Well-defined and documented technical data packages

   Changes to user capability needs

17) The Army can transfer excess funds from a Procurement appropriation to a Research, Development, Test, and Evaluation (RDT&E) appropriation to cover a funding shortfall of $3 million without prior approval of Congress.

   True

   False

18) As part of the overall systems engineering effort, both the Government and the Contractor conduct configuration management activities, and either can take the lead for a particular configuration item. The contractor is usually responsible for design and control of ___________________, while the Government is responsible for _______________.

   Integrated products /integrated processes

   Internal interfaces / external interfaces

   Technical measures / technical performance measures

   Supportability changes / sustainability changes

19) A Government official who obligates the Government on a contract without having sufficient funds to cover that expense has violated the _______________.

   Anti-Deficiency Act

   Misappropriation Act

   Reprogramming Thresholds

   Bona Fide Need Rule

Calculate Your Essay Price
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more