The writer is very fast, professional and responded to the review request fast also. Thank you.
1) When a program deviation occurs, the Program Manager should notify the Milestone Decision Authority within 90 days of the occurrence.
True
False
2) The _______ defines design requirements and is primarily documented by the Item Performance Specifications.
Allocated Baseline
Product Baseline
Functional Baseline
Maintenance Baseline
3) Who usually controls the “build to” or product baseline in an acquisition program?
DoD Information Technology Standards Registrar
Government
Contractor
Subject Matter Expert
4) The Program Manager just received approval of his proposed acquisition strategy with one exception: he has been directed to make maximum use of existing Air Force software. Which of the best software acquisition practices is most applicable to his situation?
Inspect requirements and design
Use system based software design
Use metrics to manage
Assess reuse risks and cost
5) An Early Operational Assessment is typically conducted to _____________________.
Identify potential operational effectiveness and suitability issues during system development
Support the decision to begin low rate initial production (LRIP)
Meet the requirement to conduct initial operational test and evaluation (IOT&E)
Track the evolution of critical technical parameters against the system design
6) Problem-solving models typically involve identifying all possible causes, and then narrowing down the critical causal factors to uncover the root cause.
True
False
7) Cost, schedule, and performance parameters are interrelated, and a change in one parameter can affect the others. Therefore it is important to involve all the key stakeholders when considering changes to the Acquisition Program Baseline (APB).
True
False
8) Which of the following configuration baselines is used to define the overall system level capabilities of a system?
Functional Baseline
Item Baseline
Product Baseline
Allocated Baseline
9) The primary system interoperability issue is the complete, accurate, and timely transfer of information from one system to another. In order to validate the interoperability of systems, extensive testing is required.
True
False
10) The management of internal interface design would usually be the responsibility of the _____________?
Joint Interoperability Test Command
Contractor
Government Program Manager
Independent Test and Evaluation Agency
11) When using the cause-and-effect (Fishbone) diagram to resolve an acquisition problem, after drawing out a blank fishbone diagram, the next step is to ____________________.
Identify major cause categories
Identify the root cause
Identify possible causes and contributing factors
Define the problem
12) What are some of the planning challenges that must be considered when taking commercial items and modifying them for military use (Select all that apply)?
Maintain technical data
Management of government furnished equipment
Integration
Long-term logistics support
Availability of test ranges and personnel
13) Where would the initial Functional Baseline be reviewed to ensure that it covers all the Government’s capability needs?
Critical Design Review
Preliminary Design Review
Systems Functional Review
Test Readiness Review
14) Which technical review is held during the Engineering and Manufacturing Development Phase to assess the final design after the “build to” baseline has been achieved?
Preliminary Design Review (PDR)
Test Readiness Review (TRR)
Critical Design Review (CDR)
System Requirements Review (SRR)
15) Which of the following is a benefit of integrated developmental testing and operational testing?
It minimizes the risk of compromising test objectives.
It helps to save resources by eliminating redundant activities.
It is required by law.
It simplifies the test process by making tests easier to coordinate and design.
16) Program cost increases and schedules slips are most likely caused by __________________, changes to the design, and changes to the production processes.
Changes to the number of systems ordered
Robust and accurate configuration management
Well-defined and documented technical data packages
Changes to user capability needs
17) The Army can transfer excess funds from a Procurement appropriation to a Research, Development, Test, and Evaluation (RDT&E) appropriation to cover a funding shortfall of $3 million without prior approval of Congress.
True
False
18) As part of the overall systems engineering effort, both the Government and the Contractor conduct configuration management activities, and either can take the lead for a particular configuration item. The contractor is usually responsible for design and control of ___________________, while the Government is responsible for _______________.
Integrated products /integrated processes
Internal interfaces / external interfaces
Technical measures / technical performance measures
Supportability changes / sustainability changes
19) A Government official who obligates the Government on a contract without having sufficient funds to cover that expense has violated the _______________.
Anti-Deficiency Act
Misappropriation Act
Reprogramming Thresholds
Bona Fide Need Rule
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more