Strayer BUS430 week 7 Quiz Latest 2016 Jan.

Question

Question 1

“The inability to satisfy the demand for an item” is the definition of a

a. reorder point

b. stockout

c. lost sale

d. backorder

Question 2

For the single-period inventory model, solving for the optimal order quantity involves using

a. marginal economic analysis

b. total cost analysis

c. ABC analysis

d. reorder point analysis

Question 3

Inventory position is computed using all the following except

a. On-hand

b. Scheduled receipts

c. Backorders

d. Lead time demand

Question 4

Independent demand

a. can be derived/calculated

b. is related to other SKUs

c. is also called finished goods inventory

d. needs to be forecasted

Question 5

Demand that is stable over time is called ____.

a. Static

b. Dynamic

c. Stochastic

d. Deterministic

Question 6

Demand that varies over time is called ____.

a. Static

b. Dynamic

c. Stochastic

d. Deterministic

Question 7

Average inventory in the EOQ model is defined as

a. The order quantity divided by the number of inventory cycles per year

b. Annual usage divided by the number of inventory cycles per year

c. One-half the order quantity

d. One-half the annual usage

Question 8

Additional inventory kept over and above the average amount required to meet demand is called ____ inventory.

a. Seasonal

b. Work-in-process

c. Finished goods

d. Safety stock

Question 9

Backorders ____.

a. Result from lost sales

b. Have little financial impact

c. May occur as a result of a stockout

d. Force a customer to purchase elsewhere

Question 10

Costs associated with inspecting, unpacking and putting into storage incoming inventory are components of ____ cost.

a. Ordering or setup

b. Holding

c. Shortage

d. Unit

Question 11

Costs associated with backordering a product are called ____ costs.

a. Holding

b. Shortage

c. Ordering

d. Setup

Question 12

Which of the following is not a key assumption underlining the classic economic order quantity (EOQ) model?

a. The entire order quantity arrives in the inventory at one time

b. There are only two types of relevant costs: order/setup and inventory-holding

c. Demand is assumed to be stochastic

d. Stockouts are not allowed

Question 13

Inventory that represents partially completed products waiting further processing is called ____ inventory.

a. Raw materials

b. Work-in-process

c. Cycle

d. Safety stock

Question 14

Which is not an advantage of the periodic review system?

a. Helps to control “A” items

b. Inventory need not be monitored continually

c. Useful when a large number of items is ordered from the same supplier

d. Consolidated shipments lower freight costs

Question 15

Inventory that acts as a buffer between workstations in flow shops or departments in job shops is called ____ inventory.

a. Raw materials

b. Work-in-process

c. Cycle stock

d. Safety stock

Question 16

Setting order sizes and schedules for individual subassemblies and resources by week or day fits best with which level of the generic framework for resource planning?

a. Aggregate planning – Level 1

b. Disaggregation – Level 2

c. Execution – Level 3

d. Capacity requirements planning

Question 17

Capacity requirements are computed by multiplying the number of units scheduled for production at a work center by

a. The unit resource requirements minus the setup time

b. The unit resource requirements plus the setup time

c. The unit resource requirements and then adding in the setup time

d. The unit resource requirements and then sub-tracting the setup time

Question 18

If forecast demand exceeds the total factory or supply capacity, managers might simply decide not to meet forecast demand. This decision would most likely be made at which planning level?

a. Aggregate planning – Level 1

b. Disaggregation – Level 2

c. Execution – Level 3

d. Capacity requirements planning

Question 19

____ are the total demand for an item derived from all of its parents.

a. Planned order releases

b. Gross requirements

c. Scheduled receipts

d. Planned order receipts

Question 20

Which of the following is not an aggregate planning decision option?

a. Pricing and promotions

b. Subcontracting

c. Layoffs

d. Building a new plant

Question 21

Which lot sizing rule might base the order quantity on a standard-size container or pallet load?

a. Lot-for-Lot (LFL)

b. Fixed order quantity (FOQ)

c. Periodic order quantity (POQ)

d. Gross Requirements (GR)

Question 22

The Lot-for-Lot (LFL) rule

a. Minimizes purchase or setup costs

b. Allows the firm to take advantage of quantity discounts (price breaks) by suppliers

c. Is best applied when inventory carrying costs are high and setup/order costs are low

d. Masks the true nature of dependent demand

Question 23

Which lot sizing rule might use the EOQ calculation?

a. Lot for Lot (LFL)

b. Fixed order quantity (FOQ)

c. Periodic order quantity (POQ)

d. FOQ and POQ

Question 24

The words “product family,” “budget allocation” and “long-term” fit best with which level of the generic framework for resource planning?

a. Aggregate – Level 1

b. Disaggregation – Level 2

c. Executing – Level 3

d. The MRP II Level

Question 25

The primary output of an MRP system is a time-phased report that gives all of the following except

a. The facilities managers a detailed schedule for acquiring additional factory space

b. The accounting and financial functions production information that drives cash flow, budgets, and financial needs

c. The production managers a detailed schedule for manufacturing the product and controlling manufacturing inventories

d. The purchasing department a schedule for obtaining raw material and purchased items

Question 26

Which lot sizing rule is best when inventory carrying costs are high and setup/order costs are low?

a. Lot for Lot (LFL)

b. Fixed order quantity (FOQ)

c. Periodic order quantity (POQ)

d. Gross Requirements (GR)

Question 27

A(n) ____ is a statement of how many finished items are to be produced and when they are to be produced.

a. Aggregate Plan

b. Master Production Schedule

c. Material Requirements Plan

d. Capacity Requirements Plan

Question 28

If a work center load report indicates insufficient capacity, options for correcting the problem include all of the following except

a. Revise the Bill-of-Materials

b. Change the Master Product Schedule

c. Subcontract

d. Transfer personnel between work centers

Question 29

Promotion of weekly discount airfares by an airline would be an example of ____.

a. Demand management

b. Production rate changes

c. Inventory changes

d. Facility, equipment, and transportation change

Question 30

The purpose of aggregate planning is to

a. Minimize the work force size

b. Maximize the production rate

c. Minimize the cost of meeting demand

d. Optimize the inventory level

Calculate Your Essay Price
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more