The writer is very fast, professional and responded to the review request fast also. Thank you.
QUESTION 1
A project objective
a.
lists the interrelated tasks.
b.
utilizes various resources to carry out the tasks.
c.
establishes what is to be accomplished.
d.
assigns the resources to the tasks in the project.
3 points
QUESTION 2
Which of the following is an example of a project?
a.
Directing a business internship program for students.
b.
Managing a catering business.
c.
Paving a shopping mall store parking lot.
d.
Sponsoring a sporting event.
3 points
QUESTION 3
The project objective must be agreed upon by
a.
the sponsor and the organization performing the project.
b.
the project team.
c.
the stakeholders.
d.
those responsible for each of the project tasks to be completed.
3 points
QUESTION 4
The result of the performing phase of the project life cycle is
a.
documentation of the steps necessary to complete the project.
b.
approval of the project charter.
c.
the expenditure of all the funds planned for the project.
d.
the accomplishment of the project objective.
3 points
QUESTION 5
Corrective action must be taken for a project when
a.
actual progress to the planned progress shows the progress is ahead of schedule.
b.
the actual progress is less than the planned progress.
c.
the technical specifications have been met.
d.
the actual cost of the activities is less than the funds received for the work completed.
3 points
QUESTION 6
This first phase of the project life cycle involves the:
a.
brainstorming solutions
b.
identification of a need, problem, or opportunity
c.
identifying the tasks to be performed
d.
contract negotiations
3 points
QUESTION 7
The chances of making the best decision about which projects to implement are increased by
a.
inviting a large number of stakeholders to review the projects.
b.
having a bidders’ meeting to discuss the RFP.
c.
having only one person make a decision about which projects to implement.
d.
having a well-rounded committee and well-understood evaluation criteria.
3 points
QUESTION 8
The building constructed will have at least R-38 insulation rating for the ceiling and R-28 for the walls. This is an example of the ____ in a project charter.
a.
success criteria and expected benefits
b.
acceptance criteria
c.
project objective
d.
project description
3 points
QUESTION 9
The request for proposal
a.
is the same as a project charter.
b.
is developed at the same time as the project charter.
c.
is used in every project.
d.
allows contractors to understand what the customer expects.
3 points
QUESTION 10
Project life cycles
a.
may include the funds available for completing the project during each phase.
b.
follow a rigid process that includes development of a project charter and RFP.
c.
always include the preparation of a written request for proposal.
d.
sometimes move from initiating to planning and performing phases without a formal request for proposal.
3 points
QUESTION 11
The project charter helps the team to
a.
decide which contractor to select to work on a project.
b.
determine the purpose of the project.
c.
develop a detailed baseline plan for performing the project.
d.
set the evaluation criteria to select the project.
3 points
QUESTION 12
Business customers and contractors
a.
deserve special consideration during the development of the RFP.
b.
should receive special information because they have a relationship with the customer.
c.
have an advantage over other types of contractors, e.g., government, military, or private firms.
d.
consider the RFP/proposal process to be a competitive situation.
3 points
QUESTION 13
A way to foster trust is to
a.
ask about upcoming RFPs a company is planning.
b.
get insider information about a company then share it with a competitor.
c.
be reliable and responsive.
d.
only contact the customer when planned.
3 points
QUESTION 14
Customers and partner organizations prefer to work with people they
a.
have read about.
b.
know and trust.
c.
know are lean companies with few employees.
d.
know are very large with many employees.
3 points
QUESTION 15
Contacts with potential clients
a.
occur only when there is a funding opportunity.
b.
focus on discussing potential contract opportunities.
c.
should be frequent and on a personal basis.
d.
should inform the client about the projects on which you are working.
3 points
QUESTION 16
The objective of the ____ section of the contractor proposal is to convince the customer that the contractor can do the proposed work (the project) and achieve the intended results.
a.
operational
b.
management
c.
cost
d.
technical
3 points
QUESTION 17
A BAFO requested by a customer is
a.
a best and final offer from the contractor.
b.
a best and first offer from the contractor.
c.
a base accounting and finance office clarification from the contractor.
d.
a clarification request for broad, ambiguous, frivolous, and obscure aspects of the proposal.
3 points
QUESTION 18
____ outlines the circumstances under which the contractor must notify the customer immediately of any actual or anticipated schedule delays.
a.
Approval of subcontractor
b.
Notice of cost or schedule overruns
c.
Terms of payment
d.
Misrepresentation of costs
3 points
QUESTION 19
The planning process is based on
a.
the number of risks for the project.
b.
the experience of the project’s stakeholders.
c.
the project objective.
d.
the number of resources available for the project.
3 points
QUESTION 20
The key to quality control is to
a.
have extra funds planned into the budget to pay for fast tracking the project.
b.
have an external inspector examine the final product only.
c.
rework each deliverable to make sure it is right.
d.
monitor the quality of the work early and regularly throughout the project.
3 points
QUESTION 21
In the planning process, the ____ is/are the end product(s) that the project team must deliver.
a.
cycle
b.
environment
c.
work forms
d.
objective
3 points
QUESTION 22
The project team or contractor must avoid ____, which is informally making changes to the project scope without appropriate approval.
a.
scope change
b.
scope creep
c.
updating the work breakdown structure
d.
editing the project scope document
3 points
QUESTION 23
The responsibility assignment matrix shows
a.
the primary and support responsibility for each task.
b.
dual primary roles for each work item in the matrix.
c.
the percentage of effort by the support responsibilities.
d.
the amount of time the primary responsibility is assigned.
3 points
QUESTION 24
A comprehensive project scope document is ____ the work breakdown structure.
a.
important because it is the foundation for creating
b.
not as important as
c.
not needed for creating
d.
the same as
3 points
QUESTION 25
The ____ may include a high-level WBS in a graphic chart format or as an indentured list of the work elements and associated deliverables.
a.
network diagram
b.
statement of work
c.
project scope document
d.
work breakdown structure
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more